Crews are hoping to get the third southbound lane between I-485 and City Boulevard opened by the end of March.
Here they are moving barrier wall so they can re-paint road markings.
|
(Pictures L and R) Erosion control methods are needed before southbound lanes can be opened.
|
|
|
|
New ramp to I-85 south from City Boulevard is expected to open this summer.
|
|
One of the last tasks to accomplish before lanes are opened in April: Building median barrier wall.
|
|
(Pictures L and R) Warmer spring weather will allow crews to finish the final layers of asphalt.
|
|
|
|
I-85 at City Boulevard.
|
|
Southbound lanes at City Boulevard.
|
|
Asphalt shoulders are built borthbound.
|
|
Old 29/49 brige on I-85.
|
|
The shoulder is built along the south section of the project.
|
|
|
|
Southbound lanes are almost finished!
|
|
Crews work on the 29/49 overpass.
|
|
Bridge crews lay 25 ton bridge beams over I-85 to construct the new 29/49 overpass.
|
|
Foreman Macever Duncan and crew work along the middle section of the I-85 project.
|
|
Concrete cures on the Mallard Creek Bridge.
|
|
Lights are erected along I-85.
|
|
Work continues on the 29/49 overpass at mile marker 42.5.
|
|
MSE wall is used to build the 29/49 overpass. When finished, this wall will be over 30 feet high.
|